For plots outside Chennai Metropolitan Authority limits — most of Chengalpattu, Tiruvallur, Kanchipuram — DTCP is the approval authority. Homeli files end-to-end: drawings, document compilation, online filing, fee payment, site verification, objections.
DTCP (Directorate of Town and Country Planning) regulates building approval outside CMDA limits — much of greater Chennai's outskirts. Process is similar to CMDA: architect-signed drawings, document compilation, online filing via the DTCP portal, fee payment, site verification, approval. Timeline: 35–50 days. 2026 charges for a residential 1,500 sq ft home: ~₹50,000–₹1,20,000 total (including refundable security deposit).
First step on any Chennai project: identify the right authority. Filing at the wrong one is an automatic rejection.
Total timeline: 35–50 days for clean files. Objection cycles add 15–30 days per round.
| Cost head | Range (1,500 sq ft residential) |
|---|---|
| Development charge | ₹1,500–₹3,800 |
| Scrutiny fee | ₹2,000–₹5,000 |
| Security deposit (refundable) | ₹30,000–₹65,000 |
| Infrastructure / impact | ₹2,000–₹12,000 |
| Homeli consultant fee | ₹15,000–₹40,000 |
Bottom line: ₹50,000–₹1,20,000 total, of which ₹30,000–₹65,000 is the refundable deposit. Non-refundable portion: ₹20,000–₹55,000.
A glimpse of interiors delivered for homes across Chennai and Bangalore — itemised, on time, built to last.
Living room
Modular kitchen
Master bedroom
Walk-in wardrobe
TV unit
Bedroom designTell us about your project. A senior Homeli advisor will give you straight guidance — itemised pricing, realistic timelines, no pressure, no inflated numbers.