How long will your CMDA approval really take? Here's the day-by-day schedule for a clean file (30–45 days) and what happens if objections come.
CMDA approval in Chennai 2026 takes 30–45 days for clean files and 45–75 days if objections arise. Day-by-day: site visit + drawings (days 1–14), document compilation (15–18), online filing + fees (18–20), site verification (20–35), sanctioned plan (35–45). Each objection cycle adds 15–30 days. Pre-checked files (Homeli's standard) clear most often in 30–40 days.
| Day | Activity |
|---|---|
| Day 1 | Site visit + jurisdiction confirmation |
| Days 2–14 | Drawings preparation (architectural + structural) |
| Days 14–18 | Document compilation (patta, EC, tax, NOCs) |
| Days 18–20 | Online filing + fee payment |
| Days 20–35 | Site verification by CMDA officer |
| Days 35–45 | Sanctioned plan issued |
Fast files (30–35 days):
Slow files (45–75+ days):
A glimpse of interiors delivered for homes across Chennai and Bangalore — itemised, on time, built to last.
Living room
Modular kitchen
Master bedroom
Walk-in wardrobe
TV unit
Bedroom designTell us about your project. A senior Homeli advisor will give you straight guidance — itemised pricing, realistic timelines, no pressure, no inflated numbers.