"It'll be done in a month" is the most broken promise in interior design. Here's a realistic, week-by-week timeline for Chennai homes — and the honest list of what actually causes delays.
A typical 2–3 BHK full-home interior in Chennai takes 45–60 days of execution, plus about 1–2 weeks beforehand for design, 3D and material procurement. End to end — from first site visit to move-in-ready — plan for 8–10 weeks. A modular kitchen alone takes 3–4 weeks; a single wardrobe about 1–2 weeks.
| Phase | Duration |
|---|---|
| Site visit + measurement + itemised quote | 2–3 days |
| Design + 3D + revisions + contract | 5–8 days |
| Material procurement (ply, hardware, finishes) | 12–18 days |
| Civil + false ceiling + electrical | 7–12 days |
| Carpentry — kitchen, wardrobes, units | 20–30 days |
| Painting | 5–8 days |
| Fixtures + deep clean + snag clearance | 4–6 days |
Several phases overlap — procurement runs while design is finalised, painting starts as carpentry finishes room by room. Net end-to-end: roughly 8–10 weeks for a 2–3 BHK.
| Scope | Execution time |
|---|---|
| Single wardrobe | 1–2 weeks |
| Modular kitchen only | 3–4 weeks |
| 1 BHK full home | 4–6 weeks |
| 2 BHK full home | 6–8 weeks |
| 3 BHK full home | 7–9 weeks |
| Villa / 4 BHK | 10–14 weeks |
Honest list — most delays are avoidable:
Homeli commits to 45-day delivery for a standard 2–3 BHK turnkey project, with a ₹1,000/day penalty in the contract for delays beyond day 70. We procure with our own working capital — so material isn't waiting on your payment — and use one in-house team for civil, carpentry, electrical and painting, so there are no idle handover gaps between vendors.
A glimpse of interiors delivered for homes across Chennai and Bangalore — itemised, on time, built to last.
Living room
Modular kitchen
Master bedroom
Walk-in wardrobe
TV unit
Bedroom designTell us about your project. A senior Homeli advisor will give you straight guidance — itemised pricing, realistic timelines, no pressure, no inflated numbers.